BHP Billiton
Iron Ore Asset Development Projects
Before
25,800 man-hours of engineering design work had to be completed in 8 months. Historical delays of 2 weeks and man-hour overruns of 20%.
After
Project was finished 3 weeks early.
Productivity increased by 25% with only 19,500 man-hours needed. |